Project Timelines

The project is expected to reach financial close in 2025 and is expected to be operational in 2029/2030.
Project Initiation
Project approval Date
16 Dec 2015
July 2019
Signature Date
Project Signature Date
EPC Tender
Start of EPC Tender Period
Q4 2021
Q1 2025
Financial Close
Construction Start
Q2 2025
2029
Operational